Reporting period | January 2026 |
|---|---|
Status | In progress |
Client | K15t GmbH |
Executive Summary
This Project Status Report provides an overview of progress achieved during the reporting period. The project is currently on track with respect to scope, schedule, and budget. Planned activities for January were completed as expected, stakeholder engagement remains strong, and no critical risks have been identified that would impact delivery.
Project Objectives
The objectives of the project are to:
Improve operational efficiency across key business processes
Deliver agreed project outcomes within the approved timeline and budget
Ensure consistent quality standards across all deliverables
Maintain transparent communication and reporting with stakeholders
Overall Project Status
Overall Status: on track
Schedule: On track
Budget: On track
Scope: Stable
Progress Since Last Report
During January 2026, the following activities were completed:
Finalized current-state process analysis workshops
Documented improvement opportunities and recommendations
Conducted two stakeholder alignment meetings
Updated project documentation and status tracking
Upcoming Activities
Planned activities for February 2026 include:
Validation of proposed process improvements
Development of the future-state process model
Preparation of implementation roadmap
Ongoing project status and steering updates
Key Milestones
Milestone | Planned Date | Actual Date | Status | Comments |
|---|---|---|---|---|
Project Kick-off | 05 Jan 2026 | 05 Jan 2026 | Completed | Kick-off meeting held with all stakeholders |
Current-State Analysis Completed | 20 Jan 2026 | 19 Jan 2026 | Completed | Delivered ahead of schedule |
Improvement Opportunities Defined | 30 Jan 2026 | 30 Jan 2026 | Completed | Approved by client |
Risks and Issues
Risks
Dependency on availability of key client stakeholders during design reviews
Mitigation: Early scheduling and confirmed meeting cadence
Issues
No open issues at the time of reporting
Change Requests
No change requests were raised or approved during the reporting period.
Budget Overview
Category | Planned (€) | Actual (€) | Variance (€) |
|---|---|---|---|
Labor | 45,000 | 44,200 | +800 |
Other Costs | 5,000 | 4,750 | +250 |
Total | 50,000 | 48,950 | +1,050 |
Decisions and Action Items
Decisions
Agreement to proceed with the proposed future-state design approach
Action Items
Conclusion
Good Consulting confirms that the project remains aligned with agreed objectives and timelines. Progress to date demonstrates strong collaboration and effective execution. The project team will continue to proactively manage risks and maintain clear communication to ensure successful delivery.