Project Plan
Interlingo

Timeline & Milestones

Milestone

Target Completion

Description

Discovery Complete

Week 2

Landscape assessment validated and signed off.

Architecture Approved

Week 4

Future-state design and governance model finalised.

Cloud Environment Ready

Week 6

Platforms configured and tested.

Migration Complete

Week 10

All in-scope workloads migrated.

User Enablement Delivered

Week 12

Training and adoption activities completed.

Project Closeout

Week 13

Documentation and KPI review completed.

Timeline may shift depending on customer availability, access to systems, and volume of workloads identified during discovery.

Expected Project Roadmap

Roles & Responsibilities

Role

Good Consulting Responsibilities

Client Responsibilities

Project Manager

Lead project governance, timeline, and communication.

Assign project sponsor and technical SMEs.

Cloud Architect

Design target architecture and governance models.

Review and approve designs.

Migration Engineer

Execute technical configuration and migrations.

Provide test cases and validate migrated workloads.

Adoption Lead

Deliver communication and training activities.

Ensure user participation and feedback.

Assumptions & Dependencies

  • All necessary access will be provided before project start.

  • Client subject matter experts are available during key workshops.

  • Required licenses and subscriptions are supplied by the client unless otherwise agreed.

  • Migration windows are approved and scheduled in advance.